Case study · 8th Central Pay Commission · Government of India

Live in about a month, against a date set by statute

The 8th Pay Commission was handling demands from ministries and staff associations in an Excel sheet. A working portal replaced it in about a month, with four organisations coordinating and none reporting to the others.

Client
8th Central Pay CommissionDelivered through NeGD, MeitY
Role
Project ManagerBDO India
Team
8 peopleFour organisations coordinating
Timeline
Jul to Aug 2026Live on 24 August 2026
~70 lakhcentral government employees and pensioners whose pay the Commission reviews36.57 lakh employees and 33.91 lakh pensioners, per government data
~1 monthfrom kick-off to go-live
~21,000demands on the portal today, used by about 200 people
~₹21 lakhproject value. The constraint was a date set by law, not money

The challenge

The 8th Central Pay Commission reviews pay and pensions for about 70 lakh central government employees and pensioners. Ministries, staff associations and federations send it demands. When the project started, those demands were being handled in an Excel sheet, with no clear record of who was working on which demand or what had been decided.

The Commission's term is fixed by law, so the date could not move. The portal had to be live in about a month. It had to run on open-source tools and government cloud, use the government's single sign-on and pass an external security audit. Four organisations had to work together, and none of them reports to the others.

What was done

1. Build the modules side by side.

A delay in any one module would have pushed the whole date. So the plan was cut from five sprints to two and the modules were built in parallel. It meant more coordination and a heavier load on the project manager in the middle of the project. In return, no single module could put the date at risk.

2. Replace the spreadsheet with a proper workflow.

Each demand now moves through clear stages: created, examined, sent to a ministry if needed, reviewed by a senior officer, and then placed before the Commission. Every step has a named officer and is recorded, and the record cannot be edited afterwards. It is slower than editing a spreadsheet, and officers had to learn a process instead of a file. In return, anyone can see who holds a demand and what happened to it.

3. Size it for the volume that was coming.

Demand volumes were expected to grow many times within months. Building only for launch day would have meant a rebuild inside the Commission's term, when there was no room for one.

My role

What I owned

The delivery plan and the move to parallel streams, the workflow and its rules, coordination across four bodies, reporting, and the scope of the AI layer.

What the team delivered

Build and testing of 11 modules, and the one-time data load. A team of eight, including me.

What the client decided

The Commission's rules and approvals, the hosting, network and identity arrangements run by other bodies, and the external security audit.

The result

The portal went live on 24 August 2026, about a month after kick-off, and passed an external security audit (19 to 21 August). About 21,000 demands are on it today and around 200 people use it. Demand entry went from about 50 a day to about 1,000. Officers sign in through the government's single sign-on, and the data from 14 offices that shared no common format now sits in one place.

Where AI fits

AI layer · scoped, next stage

The next stage adds AI to help officers spot duplicate demands and find the evidence a demand refers to. It only advises. A named officer makes every decision.

The lesson

When a date cannot move, decide early which other thing will take the strain. Here it was coordination effort. Naming that on the first day made the rest of the plan realistic.

The best first requirement was the spreadsheet officers already used. Each of its columns became a proper field in the portal.

In figures
Memorandumintake Demandcreation Examinationby the creator Reviewsets priority Placed forCommission Optional: ministry referraland referred-officer view ADMINPROCESSING OFFICERCREATOR ONLYREVIEWING OFFICERTERMINAL Duplicate warningbefore the form opens Priority setHigh, Medium or Low Edits allowed,and logged
Scroll sideways to see the whole diagram
One demand, one owner at every step. The spreadsheet had no state and no owner. Here each move belongs to a named role and leaves an audit entry. Four roles: Admin, Processing, Referred and Reviewing.
View the numbers as a table
StepWho moves it
Memorandum intake and assignmentAdmin
Demand creationProcessing Officer
ExaminationThe officer who created it
Ministry referral (optional, offline; reply logged)Creator
Referred-officer observation (optional)Referred Officer
Review and priorityReviewing Officer
Placed for consideration of the CommissionTerminal; later edits logged
DEMANDS CREATED PER DAY Earlier~50 Now~1,000 DEMANDS HELD ON THE PLATFORM Today~21,000 Designed for~200,000 Figures are approximate. The second chart is the volume expected within six months of launch.
Scroll sideways to see the whole diagram
Built for month six, not launch day. Creation speed rose about twenty times, and the platform was sized for about ten times the volume held today, so there was no re-architecture inside the statutory window.
View the numbers as a table
MeasureValue (approximate)
Demands created per day, earlier~50
Demands created per day, now~1,000
Demands held today~21,000
Designed for~200,000
Read the detailsTimeline, requirements, workflow rules, decisions, architecture, delivery, how AI was used and the AI layer plan
01 · Situation

A statutory commission still running on a spreadsheet

The 8th Central Pay Commission receives memoranda and demands from staff associations, ministries and federations, examines them, and places its recommendations. When I picked up the engagement, that process ran on an Excel workbook, and the Commission works against a tenure fixed in statute.

The platform had to give officers a governed workflow, take in the Commission's existing Excel data, migrated from 14 offices that shared no common data structure, and go live while coordinating four separate bodies.

02 · The constraint

The date could not move, so something else had to give

On most programmes, when requirements churn or a dependency slips, the date moves. Here it could not. So every other variable had to take the strain: the shape of the scope, the sequencing, the team structure and how coordination was run.

  • A statutory tenure fixing the delivery date
  • An Excel workbook to replace with an accountable workflow
  • Volumes expected to rise by an order of magnitude within months of launch
  • Four coordinating bodies with no reporting line between them
  • Government of India requirements for open-source technology and government-cloud hosting
03 · My mandate

Deliver it, define it, then add the AI layer

I joined on 23 July 2026 as Project Manager, leading a team of eight. I owned delivery, product and workflow definition, and stakeholder coordination. After launch, I led the move from the first operational platform towards an AI-assisted examination layer, and I wrote its scope.

04 · Timeline

From a first meeting to a live portal in about a month

Date (2026)What happened
17 to 20 JulBusiness rules worked out in a client session and consolidated into one document: roles, flow, rules and open actions
23 JulI joined; the Commission reviewed the proposal at Additional Secretary level
25 JulThe Phase 1 proposal was submitted, and the first HTML prototype was built
27 JulPrototype walked through to the CEO of NeGD, whose feedback shortened the deck
28 JulMeeting with the Commission's Member Secretary, with a structured prototype walkthrough
Late Jul to AugSprint plan cut from five sprints to two; BRD revised after client feedback; environments set up
13 AugDatabase schema documented, after 34 migrations
19 to 21 AugExternal security audit
24 AugGo-live
9 SepAs-built functional specification issued: 143 requirements
05 · Requirements

Starting from the workbook the officers already used

The Commission's own review workbook was the first requirement document. Its main sheet had 24 columns, and its reference sheets held 74 ministries, 269 demand titles, 47 sub-concerns, 38 pay levels, 6 evidence types and 7 standard remarks. Each of those became a structured field, not a free-text cell.

ArtefactWhat it held
Proposal v1.0Scope, plan, sizing, risks and deliverables
Consolidated MRMS documentRoles, flow, the rules agreed on 17 July, open actions and a glossary
BRD v0.1 to v0.2Revised after client feedback; a client query document and a forwarding note went with it
Functional specification v1.0As built, dated 9 September: 143 requirements across 11 modules, with 10 documented differences from BRD v0.1
Schema document29 tables and one view, after migration 034
Sprint plan41 stories across two sprints, 12 milestones, 7 client dependencies, 8 risks and 13 Definition-of-Done criteria
06 · Workflow and rules

Every demand moves through clear stages

A memorandum is a submission. A demand is a single point the Commission has to decide on, and it is the only unit anything is measured in. Five roles use the platform: Processing Officer, Reviewing Officer, Concerned Ministry Officer, a Dashboard and Reports user, and Admin.

The user-facing modules are Memoranda Home, Demand Creation, Examination, Referred by Other Officer, Review, Demand Management, Dashboard, and Reports and Analytics. The as-built specification groups the whole system into 11 modules.

Rules settled, and the reason for each

RuleWhy
Demand is the sole unit of measurementThe Commission acts on demands, not on submissions
Only the Reviewing Officer can place a demand before the CommissionA control point before anything reaches the Commission
Refer-back returns to the last officer who held the demandWork returns to the sender
Three closure reasons at every stage: out of scope, duplicate, no rationaleAny officer must be able to close an invalid item
A duplicate closure must link to the demand it duplicatesTraceability
Archived demands reinstate at Examination, not at the old stageA reinstated demand is reassessed
Observation notes are visible to their creator onlyProtects the author's working note
The action history and audit log are append-only, enforced in the databaseAudit integrity
Missing data is shown as "Not Specified"Make gaps visible, not hidden
The closed-without-processing bucket is labelled "Non-Actionable Demands"The client's own wording
07 · Decisions

Three calls, each with its cost

Decision 1. Parallelise the delivery rather than sequence it.

WhySequencing the modules would have put every slip straight onto the statutory date. Running them as parallel streams across two sprints moved schedule risk into coordination, which I could manage, and away from the deadline, which I could not. The original plan had five sprints, and I cut it to two.

Trade-off acceptedParallel streams cost more coordination and more of my own time in the middle of the programme, and with a team of eight that was real. It bought a delivery shape where no single module could sink the date.

Decision 2. Turn the spreadsheet into a proper workflow, not a nicer spreadsheet.

WhyA shared file has no state, no owner and no audit trail, so work stalls invisibly. I specified the demand as a state machine, from creation through examination, ministry reply, peer referral and reviewing officer to placement before the Commission, with role-based access for each officer.

Trade-off acceptedIt is slower than a spreadsheet for a single quick edit, and it asked officers to learn a process rather than a file. That is the price of being able to say who holds a demand and what happened to it.

Decision 3. Build for month six, not launch day.

WhyThe known trajectory was tens of thousands of demands within months, and about 200,000 within six. Designing for launch-day volume would have meant rebuilding inside the same statutory window.

Trade-off acceptedDesigning for roughly ten times the live volume spent effort on load the platform did not yet carry, which is hard to justify against a four-week clock. It avoided a re-architecture during the Commission's tenure, when there would have been no room for one.

Other decisions on the record

DecisionChoiceWhat it cost
Duplicate detection in Phase 1Exact match only, by a content hash; fuzzy matching waits for Phase 2Near-duplicates get through until then
EvidenceOfficers describe evidence; they do not upload itNo evidence store in Phase 1
Minimum supporting documentsRelaxed from three to none after feedbackLess enforcement
Priority on a demandRemoved at the client's directionLess ranking at intake; priority is set at review
Ministry loopOffline, with the reply recorded in the portalMinistries have no login
Creation formOne scrollable page instead of a wizardA longer form
ReferralTwo modes: comments only, or transfer of ownershipMore states to explain
Data loadScripted imports run by an engineer, not an upload screenNeeds an engineer for each load
Phase 2 AIA separate, advisory-only layer, kept out of Phase 1Efficiency gain deferred
08 · Architecture and data

A plain system, loaded from a workbook

Officersbrowser, HTTPS GOVERNMENT CLOUD Firewalland load balancer Reactweb application Node.js APISSO, roles, workflow PostgreSQL29 tables, append-only audit Document storebehind opaque references Import scriptsExcel in, hashed, contacts encrypted
Scroll sideways to see the whole diagram
A plain three-tier system, on purpose. The risk was the date, not the technology, so the stack is open source and conventional. Nothing here comes from the live environment.
View the numbers as a table
StepComponentWhat it does
1OfficersReach the platform by browser over HTTPS
2Firewall and load balancerFront the government cloud
3React web applicationThe officer interface
4Node.js APIParichay SSO, roles, tokens and workflow rules
5PostgreSQL29 tables, with an append-only audit log
6Document storeDocuments behind opaque references
7Import scriptsLoad the Excel data in, hashed, with contacts encrypted

The front end is React, the API is Node.js with Express, and the database is PostgreSQL. Officers sign in through Parichay SSO, which is live. Sessions use signed tokens bound to the device, and access is by role. The schema has 29 tables and a view. The action history and audit log cannot be changed after the fact, because the database revokes the permission and a trigger blocks it. The platform is hosted in a government cloud behind a firewall.

Loading the data

  1. Excel dumpmemoranda and demands
  2. Import scriptsfive, run by an engineer
  3. Exact-duplicate hashidentical items flagged
  4. Contacts encryptedemail and mobile
  5. PostgreSQL~21,000 demands

There was no legacy system to migrate from, so this was a one-time load of the Commission's existing Excel data, which came in from 14 offices with no common structure. Gaps in the data were surfaced as "Not Specified" instead of being filled in or hidden.

09 · Delivery

Four bodies, no reporting line, one date

Across four bodies that do not report to each other, the only levers are institutional, not managerial. Coordination ran through the proper channels rather than through requests, and the Excel data load ran as its own stream so it could not block module delivery.

WEEK 1WEEK 2WEEK 3WEEK 4 Requirements,scope freezeSSO, environments Core build: stream one Core build: stream two Integration testingUAT and trainingSecurity auditData loadGo-live The Excel data load ran as its own stream, so it could not block a module
Scroll sideways to see the whole diagram
Four weeks, with the risk moved into coordination. Parallel streams meant no single module could sink the date; the cost was more coordination, which I could manage.
View the numbers as a table
WeekWhat happened
1Requirements and scope freeze; single sign-on and environments
2 to 3Core build of the modules in two parallel streams
4Integration testing, UAT, training, security audit, data load, go-live
1 to 4Excel data load, as its own stream

Reporting ran on a fixed pattern: a weekly steering committee, and status reports to the Commission's director listing every dependency with its owner, current status and next step. I presented a progress review at Additional Secretary level. An external security audit ran from 19 to 21 August, and the platform has 748 automated checks on its dashboard.

How the delivery used AI

The programme ran as an AI-assisted lifecycle: AI support in requirements, review, delivery, discovery and documentation, with a person accountable for every output. The lifecycle is set out on the How I work.

10 · AI across the lifecycle

Where Claude helped, and where it was wrong

In use for deliveryAI examination layer: scoped, next stage

StageWhat Claude producedWhat stayed a person's call
DiscoveryAnalyses of the Excel workbook and survey dataWhich questions to ask
RequirementsBRD v0.2, the client query document, the forwarding note, the consolidated documentContent, approvals and the client's wording
DesignSingle-file HTML prototypes: five portal versions, eight dashboard versions and a Phase 2 prototypeDirection and feedback
PlanningThe sprint plan in Excel, with stories, milestones, dependencies, risks and a definition of doneThe shape of the plan and what to cut
DeploymentThe infrastructure timeline and dependency trackerEscalations
ReportingStatus, expenditure and meeting reportsWhich figures to publish
TrainingThe induction deckContent
Phase 2The Phase 2 BRD and an AI delivery reportScope

Where it was wrong

What went wrongHow it was caughtThe lesson
It produced numbers that were not in the source filesI checked every figure against the filesGround every figure in a source
It proposed duplicate detection as a new AI feature when exact-match detection already existedI read the as-built specificationRead what exists before proposing what is new
A sprint plan assumed a different database from the one builtThe specification showed PostgreSQLKeep the stack documents aligned
11 · Outcome

Live on 24 August, with the AI layer next

24 Auggo-live, 2026
~21,000demands on the platform
~200active users
~1,000demands handled a day

The platform is designed for much larger volumes than it holds today, while staying aligned to Government of India requirements for open-source technology and government-cloud hosting. Demand creation went from about 50 a day to about 1,000.

The AI layer, and what it is not allowed to do

Scoped, not builtNot part of the live platform

I wrote the scope for the AI examination layer: duplicate detection, so that the same demand arriving through several associations is recognised as one; anomaly detection; evidence matching against the memoranda a demand cites; and retrieval of the referenced sources. The objective is that officers stop reading every page to find the one that matters. It is not to automate the examination.

THE DATAEXAMINATION SUPPORT (AI)THE OFFICER Memorandaas received Demandsone per point raised Cited evidencedocuments and sources Duplicatesexact, near andcontextual matches Anomaliesitems that do notfit the pattern Evidence matchingagainst the memorandaa demand cites Source retrievalthe page that matters,not the whole file Sees suggestionswith their sources Examines and decides Every output is advisory Nothing is automatedaway from the officer Power BI is a separate layer for analytical visualisation.It does not examine, and the AI layer does not chart.
Scroll sideways to see the whole diagram
Support for the examination, not a replacement for it. The aim is that officers stop reading every page to find the one that matters. Duplicate detection groups the same demand arriving through several associations, using clustering.
View the numbers as a table
CapabilityWhat it does
Duplicate detectionClusters exact, near and contextual matches across memoranda and demands
Anomaly detectionFlags items that do not fit the pattern
Evidence matchingMatches a demand to the memoranda it cites
Source retrievalSurfaces the referenced source passage

Duplicates are graded by similarity: identical at 0.99 and above, near between 0.60 and 0.99, and related between 0.40 and 0.60. The use cases grew from seven to nine to eleven as the work was scoped. The layer is advisory only and separate from Phase 1, and the delivery is planned as a two-month split.

The division of labour is deliberate. Power BI gives analytical visualisation and the AI gives examination support. Neither is asked to do the other's job, and neither makes the decision.

12 · What I carry forward

Decide early what gives when the date will not

Where a date is genuinely immovable, the useful question is not how to go faster but which variable is allowed to absorb the risk. Naming that early, here coordination overhead, is what makes the rest of the plan honest.

Escalation and diagnosis are parallel tracks, not a sequence. Raising an issue through the right channel does not mean waiting for it.

Read what is already built before proposing what is new. Several of the places AI was wrong here were places where the as-built specification already had the answer.

Delivery under a statutory deadlineWorkflow and state-machine designGovernment stakeholder managementAI product scopingMulti-agency coordinationTechnical problem solving